What Documents Ship With a Valve Order: MRB, ITP and Test Reports
Valves arrive with a document package, and the package is what determines whether goods receipt takes one hour or three weeks. In projects the package has a name - the Manufacturing Record Book - and behind it an agreed Inspection and Test Plan that decided, in advance, who would look at what and when.
This page explains what is in that package, how the ITP works, and how to write the requirement so that inspection happens before shipment rather than after the valves reach site.
The MRB: manufacturing record book
An MRB is not a single certificate. It is a compiled, indexed record of how the order was made and tested, assembled in the order the ITP defines. For a valve order it typically contains:
| Section | Contents |
|---|---|
| Index and release sheet | What is inside, and the final signature releasing the goods |
| Material certificates | EN 10204 3.1 or 3.2 for body, bonnet, closure, stem and, where required, bolting and gaskets |
| Traceability | Heat numbers linking each certificate to the marking on each valve |
| NDT reports | Radiography, dye penetrant, magnetic particle or ultrasonic, to the extent the specification requires |
| Pressure test reports | Shell and seat tests, with pressures, durations and measured leakage |
| Dimensional and functional records | Bore, face-to-face, stroke time, torque, or as specified |
| Coating and painting | Surface preparation, system and dry film thickness readings |
| Calibration records | For instruments and switches on actuated valves |
| Non-conformance and concessions | Any deviation, and how it was dispositioned |
| Final inspection record | Signed by the manufacturer and, where agreed, by the third party |
Two things decide whether the MRB is useful. It must be indexed so a specific valve can be traced without reading 300 pages, and it must be complete at release - an MRB assembled after shipment, from photocopies, is a common source of disputes.
The ITP: who looks at what, and when
An inspection and test plan (ITP) is the schedule that sits behind the MRB. Each activity has a point that defines the purchaser's involvement:
| Point type | Meaning |
|---|---|
| Hold (H) | Work cannot proceed until the party has witnessed and signed |
| Witness (W) | The party is invited; work proceeds if they do not attend |
| Review (R) | Documents are submitted for review, no attendance |
| Surveillance (S) | Attendance at the party's discretion |
| Monitor (M) | Records only |
A typical valve ITP runs: material incoming inspection (R/H), heat treatment records (R), NDT (W), dimensional inspection (W/S), shell test (H for high-integrity scope, W otherwise), seat test (H/W), painting (S), marking and nameplate (W), final visual and packing (H/W), MRB review (R).
Hold points are the leverage. A witness point that nobody attends is a signature missed, not a schedule stop. If the schedule depends on the test being witnessed, make it a hold point and agree the notification period - typically three to five working days.
What the purchase order must say
Generic wording produces a generic package. Specify:
- The document standard and certificate type - EN 10204 3.1 or 3.2, and for which parts.
- The NDT methods and extents, by part and by weld or casting.
- The ITP: submission for approval before manufacture, with the point types named.
- The third-party inspection body, who appoints it, and who pays.
- Notification period for witness and hold points.
- Language of documents, and the format (PDF, indexed).
- Whether the MRB must be approved before shipment or supplied with the goods - this is the single biggest schedule variable.
- Number of copies, and whether originals are required.
- Packing documentation: packing list, marking instructions, and any customs documentation requirements (certificate of origin, HS code).
- Documentation for unlisted items - gaskets, bolts, accessories, spares.
Other documents that travel with the goods
Beyond the MRB, expect and specify:
- Datasheet as built, not as offered, if anything changed.
- Installation, operation and maintenance manual, in the operating language.
- Packing list with net and gross weights, dimensions, and the valve tag numbers against each crate.
- Certificate of origin and HS codes for customs clearance.
- Cleaning or preservation records for oxygen service, hydrogen service, or where the specification demands them.
- Test and calibration certificates for any instrument or actuator.
Where packages go wrong
| Problem | Prevention |
|---|---|
| Certificates arrive as photographed pages, unreadable | State file format and minimum resolution in the PO |
| Heat numbers on the certificate do not match the nameplates | Require traceability check at final inspection, with the check recorded |
| MRB approved after shipment | Make MRB approval a hold point before dispatch |
| Third party not appointed until the test is due | Agree the body at order placement; slots are the constraint, not the tests |
| Accessories undocumented | List accessories and spares explicitly in the documentation scope |
| Missing non-conformance reports | Require a concessions log even when there are no deviations - an empty log is a record too |
Related reading
- Third-party inspection on valve orders - how TPI is scheduled and what the inspector signs.
- Pressure testing: shell and seat tests - the tests the MRB records.
- EN 10204 3.1 vs 3.2 certificates - the material side of the package.
- Valve marking, nameplate and traceability - the physical end of the same chain.
- Valve lead times, spare parts and minimum quantities - where documentation sits in the schedule.