商品分类

Valve Marking, Nameplate and Traceability Requirements

Goods receipt inspection is where a documentation chain either closes or breaks. The valve is on the ground, the certificates are in the folder, and the only thing that connects them is what is stamped or riveted onto the valve body. If the nameplate does not carry the heat number, the certificate proves nothing about that valve.

This page covers what has to appear on a valve, how the marking ties back to the documents, and the checks that catch problems at receipt rather than at commissioning.

What a nameplate carries

For valves to API 6D - and in substance for most oil and gas valve standards - the marking requirement covers:

Item Example Purpose
Manufacturer's name or mark Maker's logo and name Identifies the responsible party
Valve type and model Trunnion ball, 3-piece Tells the inspector what it is meant to be
Nominal size and pressure class 6" class 600 Confirms it matches the datasheet
Body and trim material A216 WCB / 316 SS Confirms the material specified was supplied
Heat number or serial number Heat 21A4471 Links the valve to its EN 10204 certificate
Temperature rating -29 to 121 °C Confirms the service envelope
Date of manufacture 2026-09 Supports warranty and ageing checks
Standard reference API 6D The standard it was built to
Monogram or certification mark API monogram where licensed Only valid if the licence covers that product

Additional requirements commonly added by project specification:

  • Tag number on a separate, corrosion-resistant tag plate - stainless steel wire or band fixed, not painted on.
  • Flow direction arrow, cast or stamped, on check valves and any unidirectional valve.
  • Fire-safe marking where certification applies, and anti-static marking for ball valves in flammable service.
  • NACE compliance marking for sour service.
  • Certification stamp of the third-party inspector where inspection was witnessed.

Where the marking goes, and where it must not

  • Body or nameplate: normally a raised pad or a stainless nameplate fixed to the body. The nameplate is what inspectors read first, so it has to survive transport and site handling.
  • Stem area: some standards allow additional marking; it should not interfere with the stem seal or the packing gland.
  • Never on the pressure boundary in a way that creates a stress raiser. Direct stamping of heat numbers into a thin wall or a critical section is a defect, not a marking. Low-stress or dot-peen marking, or marking on a welded pad, is the correct approach - and the project specification usually says which.
  • Never repaint or over-coat a nameplate during site touch-up. It is the most common way to lose traceability before commissioning.

The traceability chain, end to end

Link Document Physical check
Heat of steel EN 10204 3.1 or 3.2 certificate Heat number on the certificate
Valve Nameplate or body marking Heat number on the valve matches
Test Shell and seat test report Serial or tag number on the report
Coating Coating report Tag number or batch
Shipment Packing list Tag number against each crate
Installation Site register Tag number against the line number in the P&ID

The chain is only as strong as the weakest link, and the usual weak link is the test report: it records a serial number that appears nowhere on the valve. Requiring the same identifier to appear on the nameplate, the test report and the packing list solves it - and it costs nothing at the manufacturing stage.

Goods receipt checks that matter

  1. Read the nameplate, do not just photograph it. Compare size, class, material and temperature rating with the datasheet.
  2. Compare heat numbers with the certificates. Every valve, every certificate. This is the check that fails most often.
  3. Confirm the tag numbers against the packing list, and against the line numbers in the project documentation.
  4. Check the orientation arrow on check valves and the flow direction stamped on unidirectional valves; installation errors usually start here.
  5. Look for the certification marks - monogram, fire-safe, NACE, third-party stamp - and confirm they are actual marks, not stickers added later.
  6. Inspect the ends and the bore. Caps fitted, no debris, no corrosion, seats undamaged; on instrument items check the fittings were not overtightened in transit by a protective plug.
  7. Check the coating for damage in transit and record it; transport damage is easiest to claim on the day of receipt.
  8. File the documents against the tag numbers in the project register. A complete package filed by order number rather than by tag is a package nobody will use at commissioning.

Common failures at receipt

Failure Consequence
Heat numbers do not match anything Valve cannot be accepted for critical service; replacement or re-certification
Nameplate missing or illegible The item is undocumented, regardless of what the folder says
Test report references a different serial The test may be valid, but the link to this valve is not established
Tag plate painted over Cost and delay; sometimes re-inspection
Certificates for the wrong size or class Common with mixed-size orders; caught only by reading the certificate, not the index
Marks added by the supplier's agent after manufacture Not acceptable where marking is a standard requirement

Related reading

Want the marking requirement written into the order?

Tell us the project's marking and traceability requirement, or send the datasheet you are working to. We will confirm what will be marked, where, and which identifier ties the valve to its certificate and test report.

Request a quote: contact form or websale@sawye.com