Claims and Warranty on Valve Orders: How the Process Works
A valve problem found during commissioning is a commercial event as much as a technical one. How it is handled in the first two days usually decides whether it ends as a replacement part and a short delay, or as a dispute that runs for months and costs more than the valve.
This page sets out the process as it normally runs in oil and gas supply, and the evidence that makes a claim straightforward. The binding terms for any specific order are those in the purchase contract; what follows is the practical sequence that makes those terms workable.
The first 48 hours
| Step | Why it matters |
|---|---|
| Stop and isolate | Do not operate a leaking or damaged valve repeatedly; each cycle can enlarge damage and destroy evidence |
| Do not repair or modify | Any intervention before the supplier sees the condition removes the ability to determine the cause |
| Photograph and record | Nameplate, tag, heat number, the leak or damage itself, and the surroundings - with something for scale |
| Record operating conditions | Pressure, temperature, medium, flow, and how long the valve was in service |
| Tag the item | Keep it identifiable; do not return it to a general store |
| Notify the supplier in writing | With the tag and serial numbers, photographs, and the conditions. A phone call is not a notification |
Written notification starts the clock. Most contracts define response periods from the date of notification, not from the date of discovery.
The evidence that settles a claim quickly
- Purchase order number, invoice, and delivery date.
- Valve tag number, serial number and nameplate photograph.
- Heat numbers, matched against the material certificates.
- The pressure and seat test reports supplied with the valve.
- Installation record: date, orientation, torque, line flushing if any.
- Operating record: pressure, temperature, medium, cycles, and whether the valve was stroked.
- Photographs of the failure and of the installed arrangement, including any strainer upstream.
- A statement of what was observed, in sequence, without conclusions.
The last point is often the difference between a settled claim and a long argument. "The valve failed" invites disagreement; "at 14:20 on 3 March, downstream pressure rose above the set point while the valve indicated closed; the valve was stroked twice with no change; photographs attached" can be investigated.
Root-cause questions that get asked
A supplier evaluating a claim will typically ask:
- Was the valve within its specified envelope? Pressure, temperature, medium, flow velocity, cycling frequency.
- Was it installed per the manual? Orientation, support, flow direction, strainer, flushing before commissioning.
- Was the medium as specified? Sour service, chlorides, oxygen, particulates and debris are the usual causes of unexpected corrosion or seat damage.
- Was it stored and preserved correctly? Elastomers degrade; a valve stored in the sun for a year is not the valve that was tested.
- Is the failure within the warranty scope? Wear parts, incorrect application and unauthorised repair are commonly excluded.
How warranty typically reads
| Element | Typical commercial practice |
|---|---|
| Period | 12 months from delivery, unless the contract states otherwise |
| Coverage | Manufacturing defects and material non-conformity against the specification |
| Exclusions | Misapplication, media incompatibility, incorrect installation, unauthorised repair or modification, normal wear of seats and seals, damage in storage, corrosion from the process |
| Remedy | Repair, replacement of the defective item, or replacement parts - at the supplier's option, as the contract states |
| Costs | Part replacement is normally covered; freight, site labour, downtime and consequential loss are typically excluded unless specifically agreed |
| Preserving the claim | Notification in writing within the contract period, with the item preserved for inspection |
Two practical notes. First, the delivery-versus-commissioning trigger matters: valves bought for a project and installed two years later often fall outside a delivery-based period. Second, consequential loss is where claims become expensive, and it is almost always excluded - which is why the operating company carries the risk through insurance, not through the supply contract.
Joint inspection, and what it achieves
For anything beyond a clear manufacturing defect, a joint inspection - on site or at a works - is the fastest route to resolution. It establishes: the condition, the probable cause, whether the item is repairable, and who bears the cost. Agree the scope of the inspection in advance, and agree that its findings will be recorded and signed by both parties.
If the parties disagree on cause, an independent laboratory or a recognised inspection body can be appointed. That is slower and costs money, but it converts an argument into a finding.
Reducing claims before they happen
| Action at order stage | Effect |
|---|---|
| State the service envelope precisely (medium, temperature, pressure, cycling) | Removes the most common root cause of disputes |
| Require the datasheet as built | Avoids discovering after delivery that the valve differs from the offer |
| Agree the inspection and test plan | Problems are found at the works, not at commissioning |
| Specify storage and preservation requirements | Protects the warranty position |
| Keep the certificates and test reports filed with the tag numbers | Evidence exists when it is needed |
Related reading
- What documents ship with a valve order - the record that makes a claim resolvable.
- Pressure testing: shell and seat tests - what the factory test did and did not prove.
- How to order: quotation, PO and payment terms - the contractual side of the same transaction.
- Shipping, Incoterms and delivery - where risk transfers, which decides who handles transport damage.